You'll find that our PMI-200 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PMI-200 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any PMI Agile Certified Practitioner (PMI-ACP) practice test comfortably within the allotted time.

Question # 141

On what should an agile team work to achieve predictable flow?

A.

Small user stories

B.

Simple acceptance criteria

C.

Lean features

D.

Lean backlogs

Question # 142

Roadmaps are defined as covering a rolling 12 months. When creating a product roadmap in an agile environment, what factor should the agile lead take into consideration?

A.

Just-in-time (JIT) refinement

B.

Stories to be released in each sprint

C.

Infrastructure updates

D.

Funding decisions

Question # 143

A team member on a self-directed team is concerned that a feature the customer wants is outside of what the team will be able to deliver. What should the team member do next?

A.

Escalate the concern to the project sponsor for necessary action

B.

Adjust the feature to make it work as needed

C.

Work directly with the customer to arrive at a suitable compromise

D.

Log this into the risk register and inform the team at the next standup meeting

Question # 144

An agile project has three more iterations before the release. There is a lot of report functionality to be created and defects to be cleared. During a daily scrum, a team member suggests a timebox spike to find a more efficient way to deliver reports.

What should the project leader do?

A.

Encourage the team to self-organize and determine how to best complete their existing work and this spike.

B.

Encourage the team to complete their just existing work since the team velocity indicates they are already struggling to meet the release goal.

C.

Direct the team to defer the spike until the next release and add the action on the backlog for prioritization.

D.

Direct the team to work on the spike immediately given the importance of reporting functionality to complete the iteration.