You'll find that our PMI-200 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PMI-200 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any PMI Agile Certified Practitioner (PMI-ACP) practice test comfortably within the allotted time.

Question # 61

An agile practitioner wants to ensure that stakeholders have current information about a project's progress What should the agile practitioner do?

A.

Regularly circulate an updated, detailed version of the project plan

B.

Frequently update the online project management office (PMO) repository site

C.

Invite the stakeholders to daily stand ups

D.

Post a project board in an area where all can view it

Question # 62

The product owner of an agile project is frustrated because the team is unable to deliver as many features as expected. The product owner asks the team to reduce test-automation levels, since the quality assurance team will test the product at project completion. The product owner expects that more features will be delivered in each iteration using this approach.

What should the agile practitioner do?

A.

Ask the opinion of key stakeholders and the client to ensure the correct approach is being used.

B.

Work with the team to use this approach and request a quality assurance iteration after every three iterations

C.

Propose to completely eliminate test automation, since this is a quality assurance function.

D.

Suggest merging the quality assurance and delivery teams to enhance each iteration's test-automation levels and reduce redundancy

Question # 63

A project was delivered in a foreign country for a big customer, but there are a lot of complaints about the way the functionality was implemented. Now there is a new project to fix the defects of the first one.

What strategy should be used to deliver it successfully?

A.

Talk with the old project manager to learn about the problems they encountered and the lessons learned.

B.

Suggest organizing a meeting in order to analyze the situation and work to find a strategy.

C.

Analyze all defects and change requests carefully to understand their root causes and act accordingly.

D.

Suggest an iterative approach including timely engagement of all key stakeholders and hold regular review meetings.

Question # 64

A scrum master is working with a team on a complex software project that is scheduled to run for 2 years with a series of product releases. The scrum master is responsible for planning the project for the next 6 months and has advised planning the project up front.

What should the scrum master do?

A.

Add the releases into a roadmap with milestones and activities.

B.

Identity dedicated tasks and activities with regular feedback loops.

C.

Deliver in small and continuous iterative releases.

D.

Identify the requirements' schedule within set time scales.

Question # 65

A development team is calculating the number of story points they have completed at the end of an iteration. Although quality assurance (QA) passed and successfully demonstrated one feature, it is not being included in the release package.

Should the team add the feature's story points to their burndown chart?

A.

Yes because the story has been tested and accepted by the business as per the definition of done (Do

B.

Yes, because the development work is complete and quality assurance (QA) and release are external dependencies.

C.

No. any work that is not released cannot be considered complete as per the definition of done (Do

D.

No, because the product owner has not reviewed the release implementation checklist for potential issues.

Question # 66

A new project starts and team members are pooled together to execute it. The team works together and moves from the forming stage into the storming stage. However, potentially destructive conflicts are now arising.

What should the agile coach do to develop members into a high-performance team?

A.

Teach the team how to work comfortably in chaos.

B.

Provide strong facilitation and conflict-resolution guidance.

C.

Allow the team to resolve issues on their own.

D.

Observe each team member and advise them on team relationships.

Question # 67

During a project's last iteration, an agile team struggled with a feature's delivery due to the lack of a required skill. The project has already incurred a five-day delay. A further delay of at least 10 days is anticipated.

What should the agile project leader have done to avoid this situation?

A.

Provided just-in-time training of the required skill to specific team members

B.

Lowered the feature's priority until a team member acquired the skill to build it

C.

Assigned the feature to another agile team that had members with the required skills

D.

Ensured that the team was comprised of cross-functional, generalized specialists

Question # 68

A customer has given a project team several requests for new features on a product. The customer is upset that the requests have been placed in the backlog and are not currently being worked on by the team.

What should the team do next?

A.

Review the feature requests and reject the most complex ones.

B.

Organize the feature requests from simple to complex.

C.

Prioritize the requests for the next sprint.

D.

Turn the requests into user stories and prioritize them.

Question # 69

A team working with a new technology faces a significant amount of uncertainty about its ability to deliver stories due to technical issues. What should the team do?

A.

Capture risks and make them visible, and use a burn down chart to focus on reducing risks early in the project.

B.

Ask the scrum master to extend the sprint's duration to allow more time to work through technical issues.

C.

Place the impacted stories on the story board, and use daily stand ups to make the product owner aware of the technical issues.

D.

Seek guidance from the development manager

Question # 70

There is a database feature requiring three members of a seven person team. A meeting is scheduled at the beginning of the sprint to go over technical needs to complete the story. Who should the Scrum Master invite to the meeting?

A.

The core team and the customer

B.

The product owner and key stakeholders

C.

The customer and the sponsor

D.

The core team and the product owner